Open Season 2017

Gas Transport Services (GTS) has initialized a new Open Season (OS2017).

This OS2017 is described in more detail in our brochure that provides you with information about the way to participate, the timetable of the OS2017 process, in general terms the procedures that will apply to this OS2017 and the neighbouring operators with whom we agreed to cooperate for marketing of capacity on the respective connection points with the systems of these operators.

This OS2017 contains four main phases:

  • Registration phase
  • Non Binding phase
  • Binding phase
  • Notification of go/no-go decision(s)
     

The indicative timetable is as follows:

1 February 2012 Start of Registration Phase
1 March 2012 Start of Non Binding Phase
14 May 2012 Start of Binding Phase
1 July 2012 End of Binding Phase (signed Precedent Agreements and Secondary Capacity Agreements must be in place)
To be determined Date of notification of go/no-go decision

 

Allocation of capacity will take place after signing of the Precedent Agreements and at the latest at the notification of the go/no-go decision.

The Open Season 2017 procedure is described in more detail in our brochure that provides you with information about the way to participate , the timetable of the OS process, and in general terms the rules and procedures that will apply to this OS. You will find this brochure here.